Each year, the Engineering Division inspects the city streets and identifies those streets that require repair or reconstruction. The condition of the pavement is evaluated and measured using a pavement condition index rating system. This approach assigns a numerical rating to each section of road being evaluated. A database tracks the pavement condition and the history of maintenance of every roadway section.

Download Street Excavation Permit

July 31, 2019
City of Parkersburg – Upcoming Milling / Paving projects:

MILLING

AUGUST 29

I. 30TH ST. (WALNUT ST. – BIRCH ST.) (EDGE MILL)

J. 32ND ST. (MURDOCH – AVERY ST.) (EDGE MILL)

M. 30TH ST. (LINDEN ST. – AVERY ST.) (EDGE MILL)

N. 29TH ST. (EMERSON – DEAD END) (EDGE MILL)

AD. 20TH ST. (DUDLEY AVE. – OAK ST.) (EDGE MILL)

AE. LATROBE ST. (19TH ST. – 20TH ST.) (EDGE MILL)

AI. 13TH ST. (MURDOCH – ANN ST.) (EDGE MILL)

AJ. AVERY ST. (16TH ST. – 18TH ST.) (EDGE MILL)

AK. BEAVER ST. (16TH ST. – 18TH ST.) (EDGE MILL)

MILLING
AUGUST 30

AM. 18TH ST. (MAXWELL AVE. – PARK AVE.) (EDGE MILL)

AU. STAUNTON AVE. (KENNER – AGNESS) (EDGE MILL)

A. WILLOWBROOK DR. 2 LOCATIONS ( EDGE MILL)

E. WEST VIRGINIA AVE. (SPRUCE ST. – HEMLOCK ST.) (EDGE MILL)

F. LEWIS AVE. (VAIR ST. – CADILLAC DR.) (EDGE MILL)

G. CADILLAC DR. (FOLEY ST. – FAIRVIEW ST.) (EDGE MILL)

AF. 20TH ST. (PEARCY AVE. – PARK AVE.) (EDGE MILL)

AH.16TH ST. (HOFF ST. – FAIRVIEW AVE.) (EDGE MILL)

V. GRAND AVE. (25TH ST. – 27TH ST.) (EDGE MILL)

PAVING

AUGUST 26

BOSLEY IND. DRIVE (PIKE ST. – DEAD END)

UNITY PLACE (PIKE ST. – DEAD END)

27TH AVE. (DAVID LEE DR. – BEVERLY ST.)

26TH AVE. (LENORE ST. – DAVID LEE DR.)

20TH AVE. (SOYER ST. – NIAGARA ST.)

HIGHLAND RD. (BILZZARD DR. – HIGHLAND PL)

 

AUGUST 27

CRESCENT ST. (18TH AVE. – 16TH AVE.)

17TH AVE. (CRESCENT – RAYON DR.)

18TH AVE. (CLEGG ST. – CRESCENT)

CLYDE ST. (11TH AVE. – 10TH AVE.)

11TH AVE. (RAYON DR. – ERIE ST.)

ERIE ST. (11TH AVE. – 9TH AVE.)

4TH AVE. (EDGELAWN – HALFWAY)

 

AUGUST 28

2ND AVE. (EDGELAWN – PICKERING ST.)

PICKERING ST. (3RD AVE. – 1ST AVE.)

9TH AVE., DOOLEY AVE. & ALLEY

11TH AVE. (WILBUR ST. – ELDER ST.)

12TH AVE. (WILBUR ST. – ELDER ST.)

 

AUGUST 29

13TH AVE. (BROADWAY AVE. – CRESCENT ST.)

8TH AVE. (MYRTLE – OLIVE ST.)

FERN ST. (7TH AVE. – 6TH AVE.)

ROSS ST. (W VA. HWY 95 – DEAD END)

SYCAMORE ST. (11TH AVE. – DEAD END)

 

AUGUST 30

11TH AVE. (PIKE ST. – HAWTHORNE ST.)

11TH AVE. (PIKE ST. – DEAD END)

12TH AVE. (MERRICK ST. – TYGART ST.)

THOMAS ST. & SCENIC DR.

LENORE ST. (9TH AVE. – DEAD END)

Paving – 09-17-19 to 09-21-19:

TUESDAY 9/17

20TH STREET (DUDLEY – OAK ST.)
BEAVER STREET (16TH – 18TH)

WEDNESDAY 9/18

AVERY STREET (16TH – 18TH)
13TH STREET (MURDOCH – ANN ST.)
RIVERVIEW DR. (27TH – DEAD END)
BARTLETT STREET (29TH – 28TH)

THURSDAY 9/19

29TH STREET (EMERSON – DEAD END)
30TH STREET (LINDEN ST – DEAD END)
BIRCH STREET (29TH ST – SHOPPING CENTER)

FRIDAY 9/20

30TH STREET (WALNUT ST. – BIRCH ST.)
32ND STREET (MURDOCH – AVERY ST.)

SATURDAY 9/21

WEST VIRGINIA AVE. (SPRUCE ST. – HEMLOCK ST.)

 

*SOME STREETS MIGHT NOT BE FINISHED IN ONE DAY*

*THE ABOVE INDICATED PORTIONS WERE ADDED FOLLOWING THE ORIGINAL PAVING SCHEDULE SUBMITTED

To assist property owners in replacing aging walkways, the City of Parkersburg has an established Sidewalk Replacement Program.  This program has enabled dozens of homeowners to replace the sidewalks in front of their property by sharing the cost with the City.  Property owners are responsible for purchasing the materials and the City provides the labor. To find out more, contact the City’s Engineering department at 304.424.8559.